Energy and Atmosphere 3 - Enhanced Commissioning

February 13, 2008 – 9:04am

Intent:

  1. To begin commissioning process early during design process
  2. Execute additional activities after systems performance verification is completed

Implementation:

  • In addition to prerequisite commissioning (EAp1):
    1. designate CxA (commissioning authority) to lead/review/oversee completion of all commissioning process activities
    2. CxA must REVIEW OPR (Owner’s Project’s Requirements), BOD (Basis of Design), and Design Documents prior to 50% CD.
    3. CxA shall REVIEW SUBMITTALS for compliance with OPR and BOD.
    4. Develop a SYSTEMS MANUAL for operating staff
    5. Verify that requirements for TRAINING STAFF & OCCUPANTS are completed
    6. REVIEW BUILDING OPERATION 8-10 months AFTER SUBSTANTIAL COMPLETION

Code:

  • none

Submittal Phase:

  • construction

Extra Credit:

  • none

More Energy & Atmosphere Credits

BACK TO TABLE OF CONTENTS

PrintThis PrintThis
  1. 2 Responses to “Energy and Atmosphere 3 - Enhanced Commissioning”

  2. According to CIRs dated 8/23/05 and 6/28/02, the independent Cx authority can be obtained anytime (even during construction), as long as the owner/design/construction team is willing to make changes based on the independent Cx authority’s review.

    By David Sungarian on Jun 24, 2008

  3. Three Tasks that the Commissioning Agent must perform:

    -Conduct at a minimum one commissionig design review of the Owner’s Project Requirements, (OPR) the Basis of Design, (BOD)and the design documents prior to the Mid Construction document phase

    -Review contractor submittals for compliance with OPR and BOD. this review is concurrent withA/E reviews and submitted to design team and the Owner. ( the review facilitates, and work out issues resulting change orders etc, does NOT change scope or in the role of accepting or rejecting submittals)

    -review building operation within 10 months after substantial completion with O&M staff and occupants. Includes plan for resolution of any outstanding issues.

    The other team members can perform
    -developing a systems manual( the as built docs are under this breakdown of tasks, plus more…)
    -verify that the requirements for training operating personnel and occupants are completed.
    ALL MUST BE IN CONSTRUCTION DOCS!

    -

    By valeria on Jul 5, 2008

Post a Comment



About Pat