Energy and Atmosphere 3 - Enhanced Commissioning
February 13, 2008 – 9:04amIntent:
- To begin commissioning process early during design process
- Execute additional activities after systems performance verification is completed
Implementation:
- In addition to prerequisite commissioning (EAp1):
- designate CxA (commissioning authority) to lead/review/oversee completion of all commissioning process activities
- CxA must REVIEW OPR (Owner’s Project’s Requirements), BOD (Basis of Design), and Design Documents prior to 50% CD.
- CxA shall REVIEW SUBMITTALS for compliance with OPR and BOD.
- Develop a SYSTEMS MANUAL for operating staff
- Verify that requirements for TRAINING STAFF & OCCUPANTS are completed
- REVIEW BUILDING OPERATION 8-10 months AFTER SUBSTANTIAL COMPLETION
Code:
- none
Submittal Phase:
- construction
Extra Credit:
- none
More Energy & Atmosphere Credits
- EA P1 - Fundamental Commissioning of the Building Energy Systems (prerequisite)
- EA P2 - Minimum Energy Performance (prerequisite)
- EA P3 - Fundamental Refrigerant Management (prerequisite)
- EA 1 - Optimize Energy Performance
- EA 2 - On-Site Renewable Energy
- EA 3 - Enhanced Commissioning
- EA 4 - Enhanced Refrigerant Management
- EA 5 - Measurement & Verification
- EA 6 - Green Power
PrintThis

2 Responses to “Energy and Atmosphere 3 - Enhanced Commissioning”
According to CIRs dated 8/23/05 and 6/28/02, the independent Cx authority can be obtained anytime (even during construction), as long as the owner/design/construction team is willing to make changes based on the independent Cx authority’s review.
By David Sungarian on Jun 24, 2008
Three Tasks that the Commissioning Agent must perform:
-Conduct at a minimum one commissionig design review of the Owner’s Project Requirements, (OPR) the Basis of Design, (BOD)and the design documents prior to the Mid Construction document phase
-Review contractor submittals for compliance with OPR and BOD. this review is concurrent withA/E reviews and submitted to design team and the Owner. ( the review facilitates, and work out issues resulting change orders etc, does NOT change scope or in the role of accepting or rejecting submittals)
-review building operation within 10 months after substantial completion with O&M staff and occupants. Includes plan for resolution of any outstanding issues.
The other team members can perform
-developing a systems manual( the as built docs are under this breakdown of tasks, plus more…)
-verify that the requirements for training operating personnel and occupants are completed.
ALL MUST BE IN CONSTRUCTION DOCS!
-
By valeria on Jul 5, 2008